The overall project entails repair and alteration of the existing land port of entry facility. Repairs include: expanded inbound and outbound canopy, enclosed vehicle search area, soft secondary inspection canopy, employee parking, and interior renovation of existing facility to meet updated Customs and Border Protection program of requirements.
Architect/engineer services were awarded to Marble Fairbanks in October 2023. The Construction Manager as Advisor was awarded April 2024. Three-phase power and geothermal heat studies are complete. The concept design phase is complete. The design development phase is currently underway.
Environmental review
The National Environmental Protection Act process is underway and a contract was awarded in early 2023.
Project timeline
Planning
Design
Construction
NEPA completion Summer 2024
Award October 2023
Completion of Design Spring 2025
Construction Award Winter 2026
SAM.gov
Next solicitation opportunity is expected Winter 2024.
Project news
Check out the latest Beebe Plain LPOE project news here, as it becomes available.
We received $3.4 billion to invest in our nation’s infrastructure and competitiveness. The law provides funding for LPOE modernization projects that will create new good-paying jobs, bolster safety and security, and make our economy more resilient to supply chain challenges — all while serving as models for sustainability and innovation.
Visit the Vermont LPOE page for an overview of BIL projects there, as well as priorities, benefits and further information.
Sustainability opportunities
We will increase energy and water efficiency (including renewable energy and fossil fuel free measures), adhere to sustainable design principles, and minimize climate risk liabilities above the minimum performance criteria in a manner that is life cycle cost-effective.
Net-zero ready
80% fossil fuel-energy generated reduction
Green Proving Ground technology
LEED Gold
Whole-building embodied carbon reduction
Community impact
We will fully modernize the port with a new administration building, new pedestrian processing lanes, new primary building, and new passenger vehicle lanes and inspection lanes. The project will help improve traffic flow and border security while decreasing wait times for travelers.
PER DIEM LOOK-UP
1
Choose a location
Error, The Per Diem API is not responding. Please try again later.
No results could be found for the location you've entered.
Get my location
OR
OR
Rates for Alaska, Hawaii, and U.S. territories and possessions are set by the Department of Defense.
Traveler reimbursement is based on the location of the work activities and not the accommodations,
unless lodging is not available at the work activity, then the agency may authorize the rate where
lodging is obtained.
Unless otherwise specified, the per diem locality is defined as "all locations within, or entirely
surrounded by, the corporate limits of the key city, including independent entities located within
those boundaries."
Per diem localities with county definitions shall include"all locations within, or entirely
surrounded by, the corporate limits of the key city as well as the boundaries of the listed counties,
including independent entities located within the boundaries of the key city and the listed counties
(unless otherwise listed separately)."
When a military installation or Government - related facility(whether or not specifically named) is
located partially within more than one city or county boundary, the applicable per diem rate for the
entire installation or facility is the higher of the rates which apply to the cities and / or counties,
even though part(s) of such activities may be located outside the defined per diem locality.