New Annex & Courthouse Renovation
GSA received funding for the design and construction of a new courthouse annex and the repair and alteration of the Ashley U.S. Courthouse. The renovation of the existing courthouse and construction of the new annex will meet space requirements of the District and Bankruptcy courts. The project also includes elevator replacement, accessibility upgrades, tenant improvements, façade repairs, roof replacement, and upgrades to mechanical, electrical, plumbing and life safety systems. The project will provide six courtrooms and eight chambers to accommodate eight judges.
Current status
The project team finalized the conceptual design for the new courthouse in February 2021.
Next milestone
Construction mobilization is scheduled to begin in summer 2021.
Project Details
Total authorized funding: $6,500,000 was appropriated in fiscal year 2004 for the design of a new courthouse. Subsequently, $97,784,000 was appropriated in FY 2016 for the design and construction of a new annex and renovation of the Ashley U.S. Courthouse.
Project delivery method: Bridging Design-Build
Anticipated milestones:
- Annex construction mobilization begins: Summer 2021
- Annex design completion: Winter 2021
- Courthouse design completion: Spring 2022
- Courthouse construction begins: Spring 2022
- Annex construction complete: Spring 2023
- Courthouse construction complete: Fall 2024
Awarded contracts:
- Design-Builder: Whiting-Turner Construction Company; partnered with:
- William Rawn Associates Architects, Inc.
- Bialosky Cleveland
- Construction Manager as Agent: Hill International
- Commissioning Agent: AECOM
For Media
News Release Nov. 2, 2020
For media inquiries, contact GSA Public Affairs Officer Tanya Schusler at tanya.schusler@gsa.gov.