GSA strives to deliver projects on-schedule and on-budget to help mitigate costly overruns and schedule delays. By keeping scope, schedule, and costs aligned, project teams can deliver projects that enable federal agencies achieve their mission at best value for the American taxpayer. The information below identifies completed capital projects schedule and budget performance.
Completed Major Construction Projects FY 21 [PDF - 53 KB]
State |
City |
Project |
Actual duration (years) |
Budget variance To final baseline |
MA |
Boston |
McCormack Federal Building exterior masonry repairs |
1.46 |
8% |
NY |
Manhattan |
Javits Federal Building |
3.44 |
13% |
NY |
Manhattan |
Weiss Federal Building elevator modernization |
2.78 |
0% |
PR |
San Juan |
Degetau Federal Building hurricane |
2.12 |
37% |
GA |
Savannah |
New courthouse annex |
3.62 |
1% |
NC |
Charlotte |
Jonas Courthouse new annex |
3.25 |
6% |
SC |
Greenville |
New courthouse |
3.81 |
6% |
DC |
Washington |
Mary Switzer Federal Building consolidation & conference center |
2.89 |
3% |