9/4/2024: NEPA Record of Decision issued.
-
9/3/2024: Public comment period concludes on NEPA Final Environmental Impact Statement (EIS).
-
8/26/2024: NHPA programmatic agreement fully executed
-
8/5/2024: GSA Section 106 Meeting to review the final version of the NHPA Programmatic Agreement.
-
8/2/2024: Final Environmental Impact Statement (FEIS) published in the Federal Register
-
5/23/2024: Comments due from Section 106 parties on the draft final Programmatic Agreement.
-
4/22/2024: GSA met with the Section 106 Consulting Parties to review the final draft Programmatic Agreement.
-
3/26/2024: GSA met with Section 106 Consulting Parties to review the revised draft Programmatic Agreement.
-
3/18/2024: GSA issued an updated version of the draft programmatic agreement to the Consulting Parties.
-
3/1/2024: Comments due from Consulting Parties on the draft programmatic agreement to complete the NHPA Section 106 process.
-
2/21/2024: GSA met with the Consulting Parties to review the draft programmatic agreement of the NHPA Section 106 process.
-
12/8/2023: Section 106 charrette with developer and industry participation
-
11/2/2023: Section 106 consulting party charrette briefing
-
10/18/2023: Section 106 charrette
-
10/31/2023: End of DEIS public comment period.
-
10/2/2023: DEIS Public Hearing
-
9/13/2023: Meeting with Section 106 consulting parties.
-
9/30/2023: Substantial completion of 208-212 S. State St site.
-
7/18/2023: Met with Section 106 consulting parties.
-
6/9/2023: Met with Section 106 consulting parties.
-
4/25/2023: Met with Section 106 consulting parties.
-
4/16/2023: Began demolition of 208-212 S. State St. building.
-
3/30/2023: Met with Section 106 consulting parties.
-
3/9/2023: Completed conditions assessment.
-
3/2/2023: Met with Section 106 consulting parties.
-
1/19/2023: Met with Section 106 consulting parties.
-
12/12/2022: Closed public scoping comment period.
-
11/10/2022: Held public scoping meeting.
-
7/22/2022: Awarded environment, historic-impact studies contract.
-